In 2011, the New Energy Economy Will Cost Coloradans…

March 11, 2011 by williamyeatman · 2 Comments
Filed under: Archive, New Energy Economy 

For all the ink that Colorado’s public officials have spilled on the subject of the New Energy Economy, there’s been little discussion of its cost.

Ex-Governor Bill Ritter, for example, recently took to the pages of the New York Times to brag about his energy legacy. While he made an unsubstantiated claim about creating “thousands of new jobs,” he ignored the inconvenient truth that Xcel’s rates increased precipitously during his tenure, despite the fact that electricity demand was down due to an economic recession.

To be sure, it’s difficult to isolate an annual cost figure for the New Energy Economy. For starters, there’s a lot of policies to investigate; as ex-Governor Ritter noted in his New York Times op-ed, he enacted a suite of expensive energy policies (57 laws, to be exact). Moreover, utility accounting is arcane and largely opaque. So discerning the sum cost of these disparate measures is not easy, which is why no one has yet calculated the annual cost of the New Energy Economy…until now.

Read more

Primer for Forthcoming PUC Decision on Boulder’s Smart Grid City

December 3, 2010 by williamyeatman · Comments Off
Filed under: Archive, HB 1365 

As the Denver Post’s Mark Jaffe noted, sometime soon the PUC is expected to make a major ruling on Boulder’s Smart Grid City (“SCG”), a pilot project for so-called “smart grid” technologies that has been much maligned for costing Xcel three times what the utility had initially estimated.

Specifically, the PUC will rule on a recommended decision by administrative law judge G. Harris Adams that approved a Settlement Agreement reached by Xcel, the PUC staff, and the Governor’s Energy Office on August 27. According to the terms of the SA, Xcel can recoup $44.5 million (about $30 million more than originally proposed) from Colorado ratepayers, but beyond this number, Xcel shareholders must pay.

Here’s a quick timeline of the SGC:

  • January 2008: Xcel announced it was looking for a city of 100,000 in its eight-state territory as a test bed for smart grid.
  • March 2008: Xcel chooses Boulder. The utility claimed that the project would cost $100 million, but that a consortium would share the costs. Xcel’s Smart Grid Consortium partners included Accenture, Current Group, GridPoint, OSI Soft, Schweitzer Engineering Laboratories and Ventyx. The utility suggested repeatedly that SGC wouldn’t necessitate cost-recovery through Colorado rate-payers, although it did not rule out that possibility.
  • Winter 2009: In Docket No. 08-520E, Xcel issued its first official estimate of SGC costs: 15.3 million.
  • May 2009: At outset of Docket No. 09AL-299E, Xcel revised its SCG cost estimate upwards to $27.9 million.
  • November 2009: Xcel again increased its SGC cost estimate, to $42.1 million. It reached a Settlement Agreement with PUC Staff that allows the utility to recoup this money from ratepayers.
  • December 2009: The PUC approved the Settlement Agreement, although it required Xcel to seek to a Certificate of Public Convenience and Necessity (“CPCN”). If Xcel failed to obtain a CPCN in a future proceeding before the PUC, then it might have to return the SGC cost-recovery that it had collected in the interim.
  • March 2010: Xcel filed for a CPCN.
  • August 2010: Xcel reached a new Settlement Agreement with PUC Staff, placing a cap on SGC cost-recovery from Xcel ratepayers at $44.5 million and allowing for the CPCN.
  • October 2010: Administrative law Judge G. Harris Adams recommended that the PUC adopt the August 2010 Settlement Agreement.

Read more